Skip to content

NVIDIA Inception Program Member

A company's capital decisions,
connected.

Every decision links to its evidence, its method,
the people around it, and what it taught us.

Capvium is the AI operating system for enterprise capital allocation and capital project portfolio decisions.

Request demo

Where capital plans meet the ground.

Connect project schedules, resource constraints and financial risk to decide what to fund, when to commit and where to adjust.

Crane operator in a hi-vis vest at the controls inside a crane cab, looking up at the load

01 Refinery turnaround

Resolve resource conflicts before they delay delivery.

Identify where shared crews and equipment constrain concurrent work, and test what added capacity changes.

Use case
Refinery turnaround planning
Decision
How should work be sequenced when crews and equipment are shared?
Capvium analysis
Resource conflicts, overloaded crews and equipment, and which activities to prioritize.
Bridge-linked offshore platform complex with pedestal cranes above open sea, a crew boat heading away
Base and stress cases A sketch of two scenario fans that start together and diverge: a base case and a lower stress case. Axes are unlabelled and no values are shown. Base Stress

02 Offshore development

Stress-test the investment before sanction.

Evaluate how cost escalation, delayed start-up and weaker revenues affect project economics and capital exposure.

Use case
Offshore development sanction
Decision
Does the development still justify sanction if costs rise and revenues weaken?
Capvium analysis
Cost, delay and revenue stress cases, downside exposure and a sized commitment.

65%

of industrial megaprojects over $1 billion failed to meet business objectives

Merrow, Industrial Megaprojects (IPA), 2011

Two workers on an elevated viaduct deck under a long orange launching gantry, set against an empty pale-blue sky
Completion forecast A sketch of a completion-date distribution with P50 and P80 markers, above a critical path in which one activity drives the finish. No dates or values are shown. P50 P80 Completion Critical path Drives the date

03 Rail construction

Quantify schedule risk before committing to a completion date.

Translate activity uncertainty and dependencies into completion forecasts, then assess the cost of delay.

Use case
Rail project completion forecasting
Decision
Which completion date can we commit to, and with what confidence?
Capvium analysis
Simulated completion dates, the activities driving delay, and what a later finish costs.

20%

longer to finish than scheduled is typical for large projects

McKinsey & Company, 2016

Technician in a hi-vis vest kneeling at an open equipment rack, wiring a junction box with tools spread on the floor

04 Data center campus

Align construction with power availability.

Evaluate how grid connections and equipment delivery affect commissioning dates and project value.

Use case
Data center fit-out timing
Decision
Should fit-out be committed now, or held until power is available?
Capvium analysis
Power and equipment dates as ranges, their effect on commissioning, and project value.

~20%

of planned data center projects could be at risk of delay from grid constraints

IEA, Energy and AI, 2025

Close portrait of a miner with a dust-darkened face and grey beard under a scuffed hard hat

05 Mine expansion

Stage expansion capital around project readiness.

Compare proceeding, phasing or deferring investment as costs and market conditions change.

Use case
Mine expansion phasing
Decision
Should phase two be sanctioned now, or early works funded first?
Capvium analysis
Value of committing now versus phasing or waiting, and capital to hold back.

64%

of active mining and metals projects over $1 billion faced cost or schedule overruns

EY, mining capital productivity, 2021

Rows of high-voltage switchyard gantries, busbars and porcelain insulators in low evening sun

06 Grid connection

Prioritize projects around shared infrastructure.

Assess how a constrained asset exposes several projects at once, and size funding for each.

Use case
Projects sharing one grid connection
Decision
Which project keeps full funding if the shared connection slips?
Capvium analysis
Exposure to a shared risk across projects, and funding sized for each.

Up to 4 years

to secure a large power transformer

IEA, Building the Future Transmission Grid, 2025

Three people at a meeting table reading printed packs, one rubbing his forehead over the page

07 Annual capital plan

Turn project priorities into capital allocations.

Determine how much to allocate to each project within budget and risk constraints.

Use case
Annual capital plan allocation
Decision
How much should each project get from a budget that cannot fund everything?
Capvium analysis
Dollar amounts per project within budget and risk limits, versus ranking by return.

1 in 3

business units received almost exactly the previous year’s capital

McKinsey Quarterly, 2012

Man in shirt and tie reading a paper pack late at night under a desk lamp beside ring binders

08 Capital reallocation

Make deferral a deliberate investment decision.

Compare funding, postponing and declining projects, with the rationale traceable to the underlying analysis.

Use case
Mid-year capital reallocation
Decision
Which projects should be funded now, postponed or declined?
Capvium analysis
Funded, held-back and zero amounts, with the reasons and inputs behind each.

$1 in 7

committed to closed World Bank-financed capital projects was never disbursed

World Bank project evaluations, Capvium analysis

Which ones. How much. What if.

  • Oil & Gas
  • Infrastructure
  • Data Centers
  • Mining & Materials
  • Power & Nuclear
  • Renewables
  • Corporate Portfolios
  • Manufacturing
Bring us one real decision

Questions about Capvium

What is Capvium?

Capvium is decision software for capital allocation and capital project portfolios. It tells capital-intensive organizations which projects to fund, how much to commit to each, and when — with the downside quantified before signature. Everyone waits for uncertainty to clear before moving capital; Capvium uses it to decide how much to move.

Who is Capvium for?

CFOs, strategy and portfolio teams, capital committees and boards, working with engineering and project-controls leaders — in oil and gas, power and nuclear, renewables, infrastructure, mining and materials, data centers, manufacturing and corporate portfolios.

What decisions does Capvium help with?

Sanction decisions, phasing and staged expansion, deliberate deferral, sequencing work around shared crews and equipment, timing construction around power and equipment availability, and allocating a capital budget across competing projects. Each project gets a recommendation — commit, stage, defer or re-size — stated in dollars.

How is Capvium different from PPM or scheduling software?

Scheduling and PPM tools run and track delivery. Capvium decides how much capital each project should get, and when, and re-sizes the plan when conditions change. It works alongside Primavera P6, Microsoft Project and your PPM suite rather than replacing them. See how Capvium compares.

Is Capvium an AI chatbot?

No. The recommendations come from quantitative analysis — Monte Carlo simulation, scenario analysis and stress-testing — and would be the same whichever language model was attached. AI is used to take in documents and to explain results in plain language.

How do we get started?

Access is by invitation. Bring one real decision and we’ll run it with you as a fixed-fee pilot; you see the output before committing to a platform tier. Pricing is quote-based and scales with the capital at stake — see pricing.

The fastest way to evaluate the engine is to point it at a decision you actually have to make this quarter. We'll run it with you.

Bring us one real decision.

Priced to the capital at stake, not the seat count.

See full pricing & features
Talk to sales →
2-minute demo coming soon We're finishing the final cut. In the meantime, book a live walkthrough and we'll show you the full platform in under 15 minutes.